Ghabawi Land Fill - 5th Cell

Construction Of Fifth Cell at Ghabawi Landfill and leachate lagoon at the existing ghabawi landfill:

Fill : 0.25 Million Excavation : 0.5 Million Cubic Meter.

Back to Projects

Project Details
Employer Greater Amman Municipality
Funded By European Bank for Reconstruction and Development (EBRD)
Year 2017
Contractor J.V Issa Taranewh & Partner & Dirar Sarira Co.
Lining Sub-Contractor Arabian Enviromental Contracting Co.
Fill 0.25 Million Cubic Meter
Excavation 0.5 Million Cubic Meter
Duration of the project 318